Table 10. Course of action for the next 7 months

Activities
How to implement them
Who will implement them
Time frame



Start
End
Appoint village representative to drafting committee
Concerned villages
Village Tshokpa
23/4/05
30/4/05
Submit list of names for drafting committee
Village Tshokpa
Limbu Gup and other two villages’ Tshokpa

30/4/05
1st meeting to institute the Lingmuteychu Watershed management Committee
Village committee representatives
RNRRC Bajo
13/5/05
13/5/05
2nd Meeting
Village committee representatives
RNRRC Bajo
21/7/05
31/7/05
Select and nominate Chairman and members
Village Tshokpas

Within 31/7/05
Awareness about outputs of the workshop
All members
RNRRC Bajo
23/4/05
Within 1 month
Present final draft of the by-laws
Plenary (or workshop)
Drafting Committee
November 05
Monitoring and Evaluation
Collective
RNRRC Bajo